Sunday, 11 November 2012

42


9 November - 11 November 2012
what a relief feelings. concentrate with report. need to finish it before final week. target want to finish it before revision week which is next week.

Thursday, 8 November 2012

Wednesday, 7 November 2012

40

5 November - 7 November 2012
presentation week. can feel butterfly in my stomach :|

1st Draft

Sunday, 4 November 2012

39

29 October - 4 November 2012
as we planned earlier , we bring the project to see our supervisor. after several testing, the problem came from the battery holder which the wire had tear-off from the casing. then we change to another battery holder and everything become okay.

then sir asked to add switch for receiver unit which intercom that will put at the house.
First type battery holder

Change to this type of battery holder



Sunday, 28 October 2012

38

22 October - 28 October 2012
as mention before, we bring the project to BMI for testing stage. this is an anxious moment because if the image cannot appear while presentation our project will consider as a failure product.

at first there is no a single image appear on the monitor. we thought it is because of the weak battery but after we have change the battery we still got the same result.

we plan to meet our supervisor later.


Sunday, 21 October 2012

37

15 October - 21 October 2012
Finally!! can take a deep breath. Our project have been finalize. it can be called finish product.

have make some testing in the house and seem it is okay. will bring the project to BMI for testing stage.

Complete Project :D


Sunday, 14 October 2012

36

8 October - 14 October 2012
after several testing and error, the coding finally have been burn into the PIC. now will integrated into the project before finalize the product.

p/s:- start continue final report..few weeks before presentation